EH-500/600 Installation Manual
Page 49
1. No ARQ losses on the RF Statistics counters.
4.1.4 Ethernet Services Test
This inspection verifies correct Ethernet services flow and error-free operation.
1. Connect PCs on both ends of the link and use software-based utilities to test for
packet-loss.
2. If available, connect a packet analyzer to the GbE port and verify that no packets
are lost.
4.1.5 Management Verification
This inspection verifies proper management of the link.
1. Verify correct management/CLI connection to both local and remote ODUs.
2. Verify management access from remote NMS stations.
4.1.6 Recording ODU Configuration
Perform the following steps after the EtherHaul ODU is commissioned and accepted:
1. Copy the Running Configuration (currently active) to Startup Configuration.
2. Save the configuration file for future records and backup.
4.2 EtherHaul Commissioning and Acceptance Form
EtherHaul Commissioning and Acceptance Form
Customer Details
Customer
Project/link name
Physical Installation Verification
Local Site
Remote Site
Site name & address
Mount type
Roof-top
Mast/Tower
Other______________
Roof-top
Mast/Tower
Other______________