SMA Solar Technology AG 6 Electrical Connection
Installation Manual SI80H-60H-OffGrid-IA-en-11 37
Fasten the clamping bracket using a M6x16
hexagon socket screw and a conical spring
washer (torque: 4 Nm ... 5.7 Nm). The teeth of
the conical spring washer must face the
clamping bracket.
6.6 Connecting the BatFuse to the Off-Grid Inverter
Risk of electric shock when the battery is connected
The off-grid inverter can start automatically from standby when the battery is connected.
Only insert the BatFuse fuse links in the course of commissioning.
Recommended minimum battery capacity
If the battery capacity selected is too low, system failures may result.
Observe the recommendations for the minimum battery capacity connected to the
DC terminal of the off-grid inverter (see Section 12"Technical Data",page144).
The recommended capacities of the individual off-grid inverters in a cluster are added to
yield the total minimum battery capacity.
Cable length and recommended conductor cross-section for the DC connection
Long cables and insufficient conductor cross-sections reduce the efficiency of the system and
impair the overload capacity of the off-grid inverter. The maximum cable length is 10 m. The
recommended minimum conductor cross-section depends on the battery voltage, the power
and the cable length between the battery and the off-grid inverter:
Off-grid inverter Cable length Conductor cross-section
SI 8.0H 5 m 70 mm²
>5m 95mm²
SI 6.0H 5 m 50 mm²
>5m 70mm²