SMA Solar Technology AG 7 Commissioning
Installation Manual SI80H-60H-OffGrid-IA-en-11 69
7Commissioning
7.1 Sequence for Commissioning
Procedure See
1 Check the wiring. Section 7.2
2 Close the off-grid inverter. Section 7.3
3If present:
Ensure that the country data sets of the PV inverters and wind
power inverters are set to stand-alone grid operation.
Inverter installation manual
4If present:
Commission the Sunny Island Charger 50.
Sunny Island Charger 50
installation manual
5If present:
Commission the GenMan.
GenMan installation
manual
5Carry out QCG. Section7.4
6 Adjust and optimise the configuration. Section 7.10 ...
Section 7.23
7 Start the off-grid system and check its functions. Section 7.24
8 Charge the battery and complete commissioning. Section 7.25 and
Section 7.26