7 Commissioning SMA Solar Technology AG
70 SI80H-60H-OffGrid-IA-en-11 Installation Manual
7.2 Checking the Wiring
Ensure that you carry out all tests relevant to the off-grid system and rectify all detected problems.
Requirement:
The off-grid inverter must be disconnected from voltage sources (see Section 8.1).
Procedure:
•Check earthing.
Check additional earthing.
Check the DC connection of the off-grid inverter.
Check the AC1 and AC2 terminals.
Check the connection of the generator.
Check the control and measuring cables.
Check the wiring of the communication products.
Check the components of the off-grid system.
Checklist for Earthing
Check item Check criterion OK Not
applicable
Enclosure opening for PE Enclosure opening is sealed with a filler-plug
or M20 cable gland.
The core cross-section of the cable must be
7 mm ... 14 mm for an M20 cable gland.
Conductor cross-section of the
PE wires at the AC1 and AC2
terminals
If one PE wire is connected, the conductor
cross-section must be at least 10 mm². If two
PE wires are connected, each conductor
cross-section must be at least 4 mm².
PE connection to earth The PE wires must be earthed for example,
by means of a connection to an earthing
busbar or a foundation earth electrode.
In a TN system, N and PE
connection
Ensure by measuring that there is a
conducting connection between N and PE.
Earthing of the battery Ensure that the battery is not earthed
unintentionally.
If the battery has been earthed intentionally,
ensure that the conductor cross-section is
sufficient (see Section 6.5"Earthing the
Battery",page36).