SMA Solar Technology AG 7 Commissioning
Installation Manual SI80H-60H-OffGrid-IA-en-11 77
Requirements:
All off-grid inverters must be closed.
All off-grid inverters must be switched off.
1. Insert the fuse links into the BatFuse, quickly connect the switch-disconnectors of the BatFuse and
then close the BatFuse (see BatFuse installation manual).
2. Switching on the off-grid inverter:
For an off-grid system with one off-grid inverter,
press the activation button on the off-grid
inverter.
In the case of a cluster, press the activation
button on the master and hold down this button
until a signal sounds. All off-grid inverters in the
cluster are then switched on.
3. When the Sunny Remote Control displays
<Init System> , press and hold the button.
A signal sounds three times and the
Sunny Remote Control displays the QCG.
Does the Sunny Remote Control not display the QCG?
You not either pressed the button too slowly or have long enough.
Press the deactivation button.
Repeat steps 2 and 3.