Chapter 6: Commissioning the Installation
This chapter describes how to activate the system, pair the poweroptimizers to the
inverter and verify the proper functioning of the system.
Removing the Inverter Cover
1. Switch the inverter ON/OFF/P switch to OFF. Wait 5 minutes for the capacitors to
discharge.
Chapter 6: Commissioning the Installation 45