Site Preparation Guide Site Preparation Checklist
Page 24
Site Preparation Checklist
Electrical Installation Requirements
• A dedicated 120/208V 3 phase 50/60hz 30A circuit has been installed.
• An electrical wire with bare leads has been supplied by the customer to connect the printer
to the facility power.
• If utilizing a LAN connection, the LAN connection is within 4 meters (14 feet) of the printer.
Environmental Requirements
• The site’s environmental temperature is between 59°F to 86°F (13°C to 30°C).
• The site’s environmental humidity is between 30% to 70%, non-condensing.
• The site’s altitude does not exceed 6561.68 feet (2000 m).
Required Installation Tasks
• GrabCAD Print software has been downloaded and installed on the user’s workstation PC.
• The Welcome Kit and startup materials have been removed from the oven chamber.