2-21
2.Basic splicing operationOptical fiber splicing
2. Basic splicing operation
If Auto start heating is set to ON,
the heating operation is automati-
cally started when the fiber is
placed into the heat shrink oven.
4: Press the Heater key ( ) or tap
the Heater icon ( ).
The heat cycle is started.
If you would like to cancel the
heating process, press the Heater
key ( ) or tap the Heater icon
( ) again.
OK
NG
Heater 2
Heater 1
Heater 1
Heater 2
When lowering the fiber onto the heat
shrink oven, use the markings on the heat
shrink oven as a reference.
60mm
40mm
Marking for the center of
the heat shrink oven
1: Open the heat shrink oven lid and
the heat shrink oven clamps.
(P.7-5 Heater clamp operation)
2: Open the hood and the fiber
coating clamps. Take out the
spliced fiber. Do not flex and bend
it.
Slide the protection sleeve (P.2-
17 ) over the center of the splice.
3: While keep applyin
g
a sli
g
ht tension
to the left and ri
g
ht fibers, lower
them onto the heat shrink oven.
The oven lid and oven clamps close
accordingly.
Splice protection

Table of Contents