THREE PHASE HI 8~12kW | Installer Manual56
What this page displays:
P(Q): It adjusts the inverter reactive power according to the set active power.
P(PF): It adjusts the inverter PF according to the set active power.
Lock-in/Pn 50%: When the inverter output active power is less than 50% rated power, it won't enter the
P(PF) mode.
Lock-out/Pn 50%: When the inverter output active power is higher then 50% rated power, it will enter
the P(PF) mode.
For the detailed setup values, please follow the local grid code.
NOTE:
Only when the grid voltage is equal to or higher than 1.05 times the rated grid voltage will the P(PF)
mode take eect.




 

 


 
















