4 Commissioning
29
4.2 Commissioning
The commissioning menu is automatically opened
the first time the Solar Inverter is connected. It helps
you make the standard settings.
For a better understanding of keyboard operation,
please also see the chapter Operation.
The commissioning of the Solar Inverter as
· a single device
· a master and slaves with several networked
devices
is described in detail in the following.
Please note:
Once the system has been commissioned, the
country can no longer be changed via the menu. To
change the country retrospectively, please contact
the technical hotline on Tel +49 (0)7531 996 77-577.
Commissioning single device
System with one Solar Inverter
Single device
1. The commissioning process starts with setting of
the display language. Select required language
with
/
.
Confirm selected language with .
2. Select the country
/
.
Confirm the country of installation.
Your Solar Inverter will only start feeding electricity
once the country of installation has been confirmed.
3. Select «Single device» with
/
.
Confirm with .