Page 5-12 Document Ref 947571-001 Rev 2
Installation Quantium 110 & 210 Installation Manual
5.5.3 PIPEWORK - SUBMERGED DISPENSERS
The Installer is responsible for supplying the riser
pipe to the heights given in section 2.4 and all
pipework and connections below the filter box
connection.
EXTERNAL FILTER BOX ONLY
1) The dispenser must be positioned directly above the
riser pipes and carefully lowered into position.
2) Remove the protective covers on the fuel supply riser pipe and on the filter
box.
WARNING : BEWARE OF FUEL SPILLAGE.
3) Connect the fuel supply pipe to the filter box or optional flange (where fitted).
4) Repeat for each hydraulic position as required.
5.6 Electrical Connections
During installation, the main switch must be switched off - ensure the main switch cannot
be switched on inadvertently.
The installation of the cables must be carried out carefully to ensure the Eex-norm is
enforced (insertion of cables via glands).
The electrical connections are compatible with all European installation practices and
typical country specific cable types. The following information is the Tokheim
recommended installation, however where differences exist in the standards relating to
installation according to country specific legislation, the local/national standards must be
employed. Electrical connections are made by either :-
•Direct wiring into a terminal rail in a WWC (refer to section 5.6.1):-
- Single Phase Suction
- Three Phase Suction
- Submerged
•Wired into a junction box in hydraulic area (refer to section 5.6.3):-
- Single Phase Suction
- Three Phase Suction
- Submerged
- Split Power option - Three Phase Suction
- Split Power option - Single Phase Suction
- Split Power option - Submerged