Quantium 110 & 210 Installation Manual Commissioning
Document Ref 947571-001 Rev 2 Page 6-7
6.3 Final Checks
•Check that all W&M requirements have been fulfilled.
•Where applicable, use the UAK to check the limit of the High Speed Diesel as per W&M
regulations.
•Where applicable, note the readings on the electronic and mechanical totalisers.
•Where applicable, clear the error counters.
•Note the type/serial number(s) of the dispenser(s).
•Complete the Arrival Quality checklists and country specific product identification forms
for the dispensers and return them to the local Sales & Service Division.
6.4 Handing over to the Station Manager
Explain to the Station Manager the working of the dispenser(s) and train him in their use
(according to the User Manual).
Together with the Station Manager, go through the Acceptation checklist to check that
everything has been delivered as ordered and is in good condition. Both the Service
Engineer/Technician and Station Manager must sign the checklist.
The Station Manager must check the unit prices.
Hand over the following documents to the Station Manager:-
•One copy of the installation report including the totals of all totalisers and the type and
serial numbers of dispenser(s).
•User Manual.
•Declaration of Conformity (usually located in the Calculator Head).
•Copy of signed Acceptation checklist (usually located in the Calculator Head).
•All keys.