HDWA-SVX001D-EN
17
NNoottee:: The chiller should remain within its protective
shrink-wrap covering during storage.
Type of Requirement
Trane Supplied
Trane Installed
Trane Supplied
Field Installed
Field Supplied
Field Installed
Foundation
• Meet foundation requirements
Rigging
• Safety chains
• Rigging shackles
• Lifting beam
Disassembly/Reassembly
(as required)
• Trane will perform or have
direct on-site supervision
of the disassembly and
reassembly work (contact
your local Trane office for
pricing)
Isolation
• Isolation pads
• Isolation pads
• Optional spring isolators, when required, are
installed by others; do NOT overload springs and do
NOT install isolation springs if they block serviceable
parts such as service valves, etc.
Electrical
• Circuit breakers
• Unit-mounted Adaptive
Frequency™ Drive (AFD)
• Harmonic filter (optional)
• Autotransformer
(optional)
• Temperature sensor
(optional outdoor air)
• Flow switches (may be
field supplied)
• Tracer® AdaptiView™
display and mounting
arm
• Electrical connections to unit-mounted AFD
• Wiring sizes per submittal and National Electric Code
(NEC)
• Ground connection(s)
• BAS wiring (optional)
• Inter-processor communication (IPC) wiring
• Control voltage wiring
• High condenser pressure interlock wiring
• Chilled water pump contactor and wiring
• Condenser water pump contactor and wiring
• Option relays and wiring
Water piping
• Flow switches (may be
field supplied)
• Condenser water
regulating valve
controller (optional;
may be field-supplied)
• Thermometers
• Water flow pressure gauges
• Isolation and balancing valves in water piping
• Vents and drain valves
• Pressure relief valves (for waterboxes as required)
Pressure Relief
• Relief valves • Vent line and flexible connector
Insulation
• Insulation (optional)
• Insulation
“Appendix B: Agility™
Chiller Installation
Completion and Request
for Trane Service,” p. 70
(HDWA-ADF001*-EN;
refer to “Appendix A:
Forms and Check
Sheets,” p. 69)
• To be completed by installing contractor prior to
contacting Trane for start-up
Chiller start-up
commissioning
(a)
• Trane, or an agent of
Trane specifically
authorized to perform
start-up of Trane®
products
Post-commissioning
transport of empty
refrigerant containers for
return or recycling
• Move empty refrigerant containers to an easily
accessible point of loading
(a)
Start-up must be performed by Trane or an agent of Trane specifically authorized to perform start-up and warranty of Trane® products. Contractor shall
provide Trane (or an agent of Trane specifically authorized to perform start-up) with notice of the scheduled start-up at least two weeks prior to the
scheduled start-up.
PPrree--iinnssttaallllaattiioonn