70
HDWA-SVX001D-EN
Appendix B: Agility™™ Chiller Installation Completion
and Request for Trane Service
IImmppoorrttaanntt:: A copy of this completed form must be
submitted to the Trane Service Agency that
will be responsible for the start-up of the
chiller. Start-up will NOT proceed unless
applicable items listed in this form have
been satisfactorily completed.
TO:
TRANE SERVICE OFFICE:
S.O. NUMBER:
SERIAL NUMBERS:
JOB/PROJECT NAME:
ADDRESS:
The following items
are being installed
and will be completed by:
IImmppoorrttaanntt:: Start-up must be performed by Trane or an
agent of Trane specifically authorized to
perform start-up and warranty of Trane
®
products. Contractor shall provide Trane
(or an agent of Trane specifically
authorized to perform start-up) with notice
of the scheduled start-up at least two weeks
prior to the scheduled start-up. EEqquuiippmmeenntt
nnoott ssttaarrtteedd bbyy TTrraannee iiss nnoott wwaarrrraanntteedd bbyy
TTrraannee..
Check box if the task is complete or if the answer is
“yes”.
1. AAggiilliittyy™™ CChhiilllleerr
☐ Installation meets foundation requirements.
☐ In place and piped.
☐ Isolation pads installed.
NNoottee:: Do not insulate the Agility
™
chiller or
adjacent piping prior to the chiller
commissioning by Trane service personnel.
The contractor is responsible for any foreign
material left in the unit.
2. PPiippiinngg
Chilled water piping connected to:
☐ Evaporator
☐ Air handling units
☐ Pumps
☐ Flow switch or flow proving device installed (if
not factory-provided)
Condenser piping connected to:
☐ Condenser
☐ Pumps
☐ Flow switch or flow proving device installed (if
not factory-provided)
☐ Cooling tower
Additional piping:
☐ Make-up water connected to cooling tower
☐ Water supply connected to filling system
☐ Does unit have freeze inhibitor? If unit has
freeze inhibitor:
☐ Verify type and concentration correct per
unit submittal
☐ Calculate and record freeze point of the
solution: ___________ (specify °F or °C)
☐ Systems filled
☐ Pumps run, air bled from system
☐ Strainers installed in entering water piping
(evaporator and condenser) and cleaned
☐ Relief valve ventilation piping installed (as
applicable)
3. FFllooww bbaallaanncciinngg vvaallvveess iinnssttaalllleedd
☐ Leaving chilled water
☐ Leaving condenser water
☐ Proper porting to measure flow and balance
4. GGaauuggeess,, tthheerrmmoommeetteerrss,, aanndd aaiirr vveennttss
☐ Installed on both sides of evaporator
☐ Installed on both sides of condenser
5. WWiirriinngg
☐ Wire size per submittal and NEC 310-16
☐ Full power available
☐ External interlocks (flow switch, pumps
auxiliary, etc.)
☐ Chilled water pump (connected and tested)
☐ Condenser water pump (connected and tested)
☐ Cooling tower fan rotation checked
☐ 115 Vac power available for service tools (as
required)
☐ All controls installed and connected
☐ If unit was disassembled for installation, all
interconnecting wiring reinstalled
☐ For CVHS and CVHM chillers, indicate type of
power distribution grounding:
☐ Solidly Grounded (Center Ground Wye)
-or-
☐ Non-Solidly Grounded (Any Delta, High