EasyManua.ls Logo

Trane Agility HDWA - Service

Trane Agility HDWA
76 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
70
HDWA-SVX001D-EN
Appendix B: Agility Chiller Installation Completion
and Request for Trane Service
IImmppoorrttaanntt:: A copy of this completed form must be
submitted to the Trane Service Agency that
will be responsible for the start-up of the
chiller. Start-up will NOT proceed unless
applicable items listed in this form have
been satisfactorily completed.
TO:
TRANE SERVICE OFFICE:
S.O. NUMBER:
SERIAL NUMBERS:
JOB/PROJECT NAME:
ADDRESS:
The following items
are being installed
and will be completed by:
IImmppoorrttaanntt:: Start-up must be performed by Trane or an
agent of Trane specifically authorized to
perform start-up and warranty of Trane
®
products. Contractor shall provide Trane
(or an agent of Trane specifically
authorized to perform start-up) with notice
of the scheduled start-up at least two weeks
prior to the scheduled start-up. EEqquuiippmmeenntt
nnoott ssttaarrtteedd bbyy TTrraannee iiss nnoott wwaarrrraanntteedd bbyy
TTrraannee..
Check box if the task is complete or if the answer is
“yes”.
1. AAggiilliittyy CChhiilllleerr
Installation meets foundation requirements.
In place and piped.
Isolation pads installed.
NNoottee:: Do not insulate the Agility
chiller or
adjacent piping prior to the chiller
commissioning by Trane service personnel.
The contractor is responsible for any foreign
material left in the unit.
2. PPiippiinngg
Chilled water piping connected to:
Evaporator
Air handling units
Pumps
Flow switch or flow proving device installed (if
not factory-provided)
Condenser piping connected to:
Condenser
Pumps
Flow switch or flow proving device installed (if
not factory-provided)
Cooling tower
Additional piping:
Make-up water connected to cooling tower
Water supply connected to filling system
Does unit have freeze inhibitor? If unit has
freeze inhibitor:
Verify type and concentration correct per
unit submittal
Calculate and record freeze point of the
solution: ___________ (specify °F or °C)
Systems filled
Pumps run, air bled from system
Strainers installed in entering water piping
(evaporator and condenser) and cleaned
Relief valve ventilation piping installed (as
applicable)
3. FFllooww bbaallaanncciinngg vvaallvveess iinnssttaalllleedd
Leaving chilled water
Leaving condenser water
Proper porting to measure flow and balance
4. GGaauuggeess,, tthheerrmmoommeetteerrss,, aanndd aaiirr vveennttss
Installed on both sides of evaporator
Installed on both sides of condenser
5. WWiirriinngg
Wire size per submittal and NEC 310-16
Full power available
External interlocks (flow switch, pumps
auxiliary, etc.)
Chilled water pump (connected and tested)
Condenser water pump (connected and tested)
Cooling tower fan rotation checked
115 Vac power available for service tools (as
required)
All controls installed and connected
If unit was disassembled for installation, all
interconnecting wiring reinstalled
For CVHS and CVHM chillers, indicate type of
power distribution grounding:
Solidly Grounded (Center Ground Wye)
-or-
Non-Solidly Grounded (Any Delta, High

Table of Contents

Related product manuals