HDWA-SVX001D-EN
69
Appendix A: Forms and Check Sheets
The following forms and check sheets are included for
use with Trane start-up of HDWA Agility™ chillers.
Forms and check sheets are used, as appropriate, for
installation completion verification before Trane start-
up is scheduled, and for reference during the Trane
start-up.
Where the form or check sheet also exists outside of
this publication as standalone literature, the literature
order number is also listed.
• “Appendix B: Agility™ Chiller Installation
Completion and Request for Trane Service,” p. 70
(HDWA-ADF001*-EN)
• “Appendix C: Settings,” p. 72
• “Appendix D: Operator Log,” p. 74
Unit Start-up/Commissioning
IImmppoorrttaanntt:: Start-up must be performed by Trane or an
agent of Trane specifically authorized to
perform start-up and warranty of Trane
®
products. Contractor shall provide Trane
(or an agent of Trane specifically
authorized to perform start-up) with notice
of the scheduled start-up at least two weeks
prior to the scheduled start-up.