28
While the Digital Mixer Shower is in commissioning mode all other
functionality is locked out.
Ensure that the isolating valves on the hot and cold inlets connectors are fully on (Fig.11).
Turn on the water supplies and check the entire installation for water leaks.
Commissioning MUST be carried out with suitable pipework/hose attached to the shower
outlet and with the outlet directed to waste.
Commissioning is to ensure water is purged through the unit and any air is dispelled from
the system.
DO NOT run the low pressure Digital Mixer Shower (Pumped version) without water.
Failure to commission the Digital Mixer Shower correctly could cause
long term damage to the shower.
Turn on the electrical supply to the Digital Mixer Processor unit.
Wireless connectivity only
With batteries fitted into the Digital Controller, electricity supply to the Digital Processor
unit turned on, the wireless connectivity between the Digital Controller and Digital Mixer
Processor unit will be automatically undertaken.
If however either of the messages in Fig. 26 are displayed on the Digital Controller
permanently then wireless connectivity should be undertaken manually.
To manually connect the Digital Controller with Digital Mixer Processor unit, ensure that fully
charged batteries are fitted into the Digital Controller.
1 Isolate the electricity supply to the Digital Mixer Processor Unit
2 After at least 1 minute restore the electricity to the Digital Mixer Processor Unit
3 Within 2 minutes press and hold the ow control buttons together and hold
themdown for at least 5 seconds.
4 Wireless connectivity should now be reset, if this does not resolve the loss of
connection, this process can be repeated.