Chapter 4 - Horizontal empennage
4.1 - Assembly preparation
Page 29
4.1.2 Elevator Spar
Measure 1.5 inches behind the elevator cut line and draw a line from BL-57 L to
BL-57 R. This line will locate the front face of the elevator spar. Separate the two outer
parts of the elevator spar and remove the back shell and core from the central area where
the phenolic material will be placed. Glue the phenolic part in place of the material
removed with epoxy for 5 minutes. Position the spar as mentioned above, remembering
that the straight face is positioned upwards.