2.9.3 Both Power Bus Failure
Should both power buses be replaced by generator after a fault sequence of both the power
buses, the Liebert MBSM will do the following:
If local priority switch is on auto, the Liebert MBSM will select one of the two generators as a source for
system synchronization.
If local priority switch is on a preferred source, that source will be selected, unless the voltage and
frequency values are outside preset limits; under this last condition the second available source will be
selected anyway, independently from the switch position.
If both sources are detected outside set limits, the Liebert MBSM will generate the frequency reference
by the local quartz oscillator.
If the two power buses are supplied from a common generator and inside set limits, the Liebert MBSM will
operate as per normal conditions and checks