This section is an overview of the steps required to commission an Aprisa SR radio network in the field:
Ensure that the site preparation is complete:
Power requirements
Tower requirements
Environmental considerations, for example, temperature control
Mounting space
Connect earthing to the radio.
Confirm that the:
Antenna is mounted and visually aligned
Feeder cable is connected to the antenna
Feeder connections are tightened to recommended level
Tower earthing is complete
Install lightning protection.
Connect the coaxial jumper cable between the lightning protection and the
radio antenna port.
Connect the power to the radio.