Commissioning
Preconditions:
All PLC modules are installed and wired according to the configuration in Automation
Builder.
The PLC is connected to the power supply.
The application and the necessary licenses are available.
WARNING!
Risk of injury or damage to equipment
To avoid endangering persons or equipment, check before commissioning:
Mechanical and electrical installation
Electrical safety of the installation
Safety functions
1. Switch on the power supply.
ð
The green PWR LED goes on.
ð
Processor modules with display: W
ait until the processor module displays “Update”.
2. Install the firmware and the application on the processor module.
Installing the firmware and the application on a very new processor module is the same
process than updating a firmware and an application on a CPU.
Ä
Chapter 9.2 “PLC firmware/application update” on page 86
ð
The PLC starts with the new firmware and the new application.
WARNING!
Risk of injury or damage to equipment
T
o avoid endangering persons or equipment, a functional test of the applica-
tion must be performed before the final commissioning of the system.
Preconditions:
The control panel is installed and wired.
The control panel is connected to the power supply.
The project file and the necessary licenses are available.
1. Start the control panel.
2. Set the IP address of the control panel.
3. Download the project file to the control panel.
4. Connect the PLC and the control panel with an Ethernet cable.
Commissioning
the PLC
Commissioning
the control
panel
Commissioning