04-3275_OPM_ABB_CONCEPTPOWER_DPA_500kW_EN_REV-A.docx Page 32/78 ABB
Modifications reserved
If the UPS-CABINETS are paralleled, the Parallel Adapter will be placed on the Connector JD8 on the
distribution panel and the communications cables between the cabinets will be connected through the
connectors JD5 and JD6, as we are doing now.
NOTE: set the Switch SW2-2 correctly according to the corresponding cabinet configuration.
Figure 15: Parallel Adapter and DIP Switch SW2-2
6.2.3 DIP Switch SW1-6
SW1 1 SW1 2 SW1 3 SW1 4 SW1 5 SW1 6 JP1
6 Dip switches are mounted on it and the setting for the parallel configuration must be
done according to the above table.
The Jumper JP1 must be always present (inserted) on all boards inside the parallel
system (single or more frames working in parallel)
The new connector “X1” is used only in case the UPS is equipped with the “synchronization
with main” feature.
specific “special project” is present on all modules inside the system)
In this case the reference “Mains” (phase & neutral) has to be connected to “X1” and the
jumpers JP2, JP3 & JP4 mounted inside the board correctly set according to its voltage (See
table below)
Mains on X1 JP2 JP3 JP4
480V
OFF OFF OFF
230V ON ON
OFF
120V ON ON ON