EasyManua.ls Logo

ABB Conceptpower DPA 500 - Options; On Request; Installation Planning - Ups Positioning; Heat Dissipation

ABB Conceptpower DPA 500
81 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
04-3275_OPM_ABB_CONCEPTPOWER_DPA_500kW_EN_REV-A.docx Page 77/78 ABB
Modifications reserved
10.8 OPTIONS
- Maintenance bypass
- SNMP cards
- Battery Cabinet
- Parallel KIT for paralleling multiple frames
- Wooden box
- Temp. sensor for battery temp. control
10.9 ON REQUEST
- INPUT / OUTPUT transformers for galvanic isolation or special voltages
- Bypass transformer
- IP 21
10.10 INSTALLATION PLANNING UPS POSITIONING
Clearances needed to allow proper airflow on the UPS system and to allow door opening.
Minimum clearances for single UPS
UPS Model
A
1
(mm)
B
1
(mm)
C
(°)
D
(mm)
DPA 500 300 1000 115° 400
Minimum clearances for UPS + other cabinets in row
UPS Model
A
2
(mm)
B
2
(mm)
C
(°)
D
(mm)
DPA 500 300 1000 115° 400
Top view and indication of the minimum clearances for
single UPS.
Top view and indication of the minimum clearances for UPS +
other cabinets in row .
10.11 HEAT DISSIPATION
Module quantities 1 2 3 4 5
UPS power rating kW 100 200 300 400 500
Heat Dissipation with 100% linear load
W 4500 9000 13500 18000 22500
BTU
15359
30717
46076
61434
76793
Heat Dissipation with 100% non-lin.load
(acc. to IEC 62040-3)
W
5710
11420
17130
22840
28550
BTU
19488
38976
58465
77953
97441
Airflow (2- 30°C) with 100% non-lin. Load
(acc. to IEC 62040-3)
m
3
/h 1200 2400 3600 4800 6000
Heat Dissipation without load W 660 1320 1980 2640 3300
B
1
A
1
UPS
Cabinet
door
opening
C
D top clearance
is only needed if
there is no side
clearance.
B
2
UPS
Cabinet
A
2
Battery cabinet
or other
equipment
Battery cabinet
or other
equipment
door
opening
C