Component Installation and Disassembly Procedures
6-3
• Measure each length of branch cable and order the appropriate
branch cable spools. Refer to page 8-11 for spool sizes and related
part numbers. Consider service loops — order 10% longer cable
lengths. NO SPLICING — BRANCH CABLE RUNS MUST BE
CONTINUOUS.
• Prepare the sites:
– Ensure sites conform to environmental specifications.
– Install AC power receptacles within 1.8 m (6 ft.) of instruments
connected to the SDN, and install AC power receptacles within
1.5 m (5 ft.) of the ACC.
– Install wall mounts, consoles, etc. for mounting monitoring and
display instruments.
• Supply and install branch cable enclosures (conduit, troughs,
raceways, etc.) when necessary.
• Supply and install NEMA switch wall boxes near each instrument (2
3/4-inch depth minimum with conduit knockouts).
• Receive and store equipment and instruments.
• Install and test UTP cable using Category 5 rules with AMP 110 edge
connectors.
• Supply a standard 19" telecommunications rack or:
• Mount a plywood panel 40.6 cm wide x 50.8 cm high x 1.9 cm deep,
minimum (16 in. W x 20 in. H x 3/4 in. D) to wall surface at the
chosen ACC site location. DO NOT MOUNT ACC TO WALL
SURFACE.
• Install branch cables from plywood panel (ACC site location) to the
switch wall boxes. Leave at least a 4-foot service loop at the plywood
panel (ACC).
• Supply certification of Category 5 UTP installation to Agilent
installer.
• Ensure cable installation conforms to local building codes.
• Schedule Agilent Technologies service personnel to interconnect
parts and instruments of the SDN.
• Schedule key operator training for SDN system operation.
Agilent Installation Responsibilities
• Assist customer in planning system configuration.
• Inspect each instrument site for conformance to environmental
specifications and service access requirements.
• Supply system distribution branch cables, connectors, and
faceplates.
• Mount the ACC to the plywood panel or rack mount.
• Connect branch cables to each wall box.
• Connect branch cables to the ACC.
• Install the instruments.
• Connect the instruments to the SDN.
• Perform comprehensive system verification procedures.
• Train key operators to ensure proper SDN system operation.