5. Pre-Installation Preparation
5.1 Site Selection
The power system must be mounted in a clean and dry environment.
Consider both the floor loading and the physical space required for the CXPS-C power system and the batteries:
Dimensions for one bay:
mm: 2133H x 711W x 711D
Inches: 84H x 28W x 28D
Avoid areas that may be subjected to hot air exhaust from nearby equipment.
Provide adequate space for safe installation and maintenance personnel
Rear: 3ft (1m) [Space not required if top access is provided for power bay]
Front: 3ft (1m)
Sides: no clearance required
Top: clearance required for cables and external return bar (optional)
5.1.1 Floor Plan Layout
Sufcient free space must be provided at the front of the power system to meet the cooling requirements of the
rectifiers in the power system and to allow easy access to the power system components.
Consider the following before selecting a location for the CXPS-C power system
Structure of building able to support the additional weight
Enough space to meet requirements for access
Enough space to meet cooling requirements of the rectifiers
Adequate space to do the install
Route that equipment will take through the building to reach the site
Check and record distances to load
Check and record distances to AC power source
Check and record distances to batteries/DC power source
Understand the full load on the DC system
Window for working hours and other similar restrictions
How much and what kind of prep work can be done in advance
Reinforce floors
Install distribution panels
Install cable racks
Run wiring
Minimize cable lengths
Minimize cable flow and congestion