Prerequisites
Issue 2.1 June 2006 751
Presite migration checklist
Before you go on site, complete the following tasks:
Before you go on site, complete the following additional tasks:
9
Task Description
Verify that the voice network,
dial plan, and E911 for remote
locations were redesigned.
Perform this task only if applicable.
Verify that all existing circuit
packs work with the new
system.
Check the Minimum Vintage Table. Go to the
Hardware and Software Compatibility Matrix at ftp//
ftp.avaya.com/incoming/Up1cku9/tsoweb/media/
minhardwarevintages.pdf.
Replace any TN799B/C C-LAN
circuit packs.
Replace with the TN799DP circuit pack.
Replace the 259A adapter and
the CAT3 cable.
Replace with the cable extender adapter with
Comcode 848525887 and the CAT5 or better cable.
Replace TN570 EI circuit packs. Replace with TN570B vintage 7 or later circuit packs.
9
Task Description
Replace the TN570 EI
circuit packs.
If you also are installing an ESS server, replace with
TN570D or later circuit pack.