If, conversely, the label 200-240 and its corresponding
arrow points to the arrow directly below the Fuse Holder,
you must plug your unit into a 240 VAC power source.
Your Atomlab 100 has already been configured for
your use. If, however, you turn the Fuse Holder upside
down to change the voltage required, the fuses within the
Fuse Holder must have the proper rating. See Appendix A
for details.
3) Locate the Power Switch to the right of the Fuse Holder
and the socket for the Power Cable to the left.
4) Ensure the Power Switch is in the OFF position (0).
5) Plug the Power Cord into the socket.
6) Rotate the Display Unit back to its normal position.
7) Take the remaining end of the Power Cord and plug it
into an outlet which meets the requirements previously
outlined.
POWERING UP
Reach behind the Display Unit and power up your Atomlab
by flipping the Power Switch from the 0 (OFF) position to the
– (ON) position. The Self-Test will commence automatically.
Because the Atomlab 100 is capable of using multiple
Chamber Units, the Self-Test for this system checks to see if
more than one Chamber is in use. This causes the Self-Test
to pause approximately 20 seconds after power up. To com-
plete the test and place the unit in normal operating mode,
press the ENTER key when it begins to flash.
If an error is detected on either system, it will be noted on
the Electronic Thumbwheel Display. You can then refer to
Appendix A or the Trouble-shooting Guide supplied with this
manual to resolve the problem.
ATOMLAB Dose Calibrator Operation Manual Chapter 2
Biodex Medical Systems 2-6 Release 2.0