DateTimeVerified ByPlanning ActivityTask No.
Cable and interface
equipment
evaluation:
• Cable type
• Connector type
• Cable distance
limitations
• Interface
equipment
(transceivers)
5
EMI evaluation:
• Distance
limitations for
signaling
• Site wiring
• RFI levels
6
2
Verify that the power supply installed in the chassis has a dedicated AC source circuit.
3
UPS: uninterruptable power supply.
4
EMI: electromagnetic interference.
5
RFI: radio frequency interference.
Contact and Site Information
Use the following worksheet to record contact and site information.
Table 11: Contact and Site Information
Contact person
Contact phone
Contact e-mail
Building/site name
Data center location
Floor location
Address (line 1)
Address (line 2)
Cisco UCS X9508 Server Chassis Installation Guide
119
Site Planning and Maintenance Records