Preparing for Installation
Jan 28 , 2011
Before you install your new appliance, carefully unpack your appliance and make sure that all parts were delivered. Once
you are satisfied that your appliance has been delivered to your expectations, verify that the location where the appliance
will be installed meets temperature and power requirements and that the server cabinet or floor-to-ceiling cabinet is
securely bolted to the floor and has sufficient airflow.
Only trained and qualified personnel should install, maintain, or replace the appliance, and efforts should be taken to ensure
that all cautions and warnings are followed.
Unpacking the Appliance
The hardware accessories for your particular appliance, such as cables, adapters, and rail kit, vary depending on the
hardware platform you ordered. Unpack the box that contains your new appliance on a sturdy table with plenty of space
and inspect the contents.
Use the following list to verify that you received everything that should have been included in the box.
The appliance you ordered
One RJ-45 to DB-9 adapter
One 6 ft RJ-45/DB-9 cable
The following list specifies the number of power cables included for each appliance model:
One power cable for the SDX 8015/8400/8600 appliances
Two power cables for the SDX 11500/13500/14500/16500/18500/20500, SDX 11515/11520/11530/11540/11542, and
SDX 17500/19500/21500, SDX 17550/19550/20550/21550, SDX 14020/14030/14040/ 14060/14080/14100, SDX
14020-40G/14040-40G/14060-40G/14080-40G/14100-40G, SDX 14040-40S/14060-40S/14080-40S/14100-40S, and
SDX 14030 FIPS/14060 FIPS/14080 FIPSappliances
Four power cables for the SDX 22040/22060/22080/22100/22120 and SDX 24100/24150 appliances
Note: Make sure that a power outlet is available for each cable.
Note: For Brazilian customers, Citrix does not ship a power cable. Use a cable that conforms to the ABNT NBR
14136:2002 standard.
One standard 4-post rail kit
Note: If the kit that you received does not fit your rack, contact your Citrix sales representative to order the appropriate
kit.
In addition to the items included in the box with your new appliance, you will need the following items to complete the
installation and initial configuration process.
Ethernet cables for each additional Ethernet port that you will connect to your network
One available Ethernet port on your network switch or hub for each NetScaler Ethernet port you want to connect to
your network
Note: Transceiver modules are sold separately. Contact your Citrix sales representative to order transceiver modules for
your appliance. Only transceivers supplied by Citrix are supported on the appliance.
A computer to serve as a management workstation
Preparing the Site and Rack
There are specific site and rack requirements for the NetScaler appliance. You must make sure that adequate environmental
control and power density are available. Racks must be bolted to the ground, have sufficient airflow, and have adequate