Figure 5. No Side Push Label
IMPORTANT: The rack may only be moved up or down a maximum incline/decline of 5 degrees.
3. Position the rack to its final location and lower the leveling feet using a 13mm wrench.
4. Use a bubble level to verify the rack is level.
5. From the bottom up, repeat the steps above to insert the disk drives into the remaining enclosures. See Install
Disk Drives in a 5U84 Enclosure on page 19 and Install Disk Drives in a 2U24 Enclosure on page 25.
Move the Rack to its Final Position