Field Settings ESIE05-04
4–20 Part 4 – Commissioning and Test Run
3
1
4
5
2.10 The Field Setting Levels
Introduction The three field setting levels are:
Q Inspection level
Q Monitoring level
Q Maintenance mode settings.
The inspection level The inspection level is the highest level of the three field setting levels. You can change the views in
the inspection level by pressing the INSPECTION/TEST button.
The flow chart below explains the different windows of the inspection level.
Normal display
Last occurred
malfunction
Indoor model and size
System
Test
Push INSPECTION/TEST button
See possible system
settings.
Push INSPECTION/TEST button
Push INSPECTION/TEST button
Push
INSPECTION/TEST
button
Push INSPECTION/TEST button

Table of Contents