SM-200 TE Grinding and Honing Machine 27
Putting the Machine into Operation
7
7. Putting the Machine into Operation
Please take the following points into account when choosing
a place to set up the machine:
• The place must provide the space required for operating and
installing the machine as well as for maintenance and servic-
ing work.
• A power connection with the necessary features is available.
7.1 Installing the machine
Place the SM-200 TE grinding and honing machine on a flat, non-
slip surface to ensure that the grinding and honing machine does
not slip, tilt or move when it is being used.
Place the SM-200 TE grinding and honing machine without a stand
on a stable table or other substructure, which has sufficient stability
to carry the weight of the machine.
1 Align the grinding and honing machine horizontally by means
of the height-adjustable machine feet [1].
TAKE ACCOUNT OF THE ERGONOMICS
• Set up the SM-200 TE grinding and honing machine in such a
way that it is possible to work safely with an upright posture.
• Ensure there is good lighting at the work area.
Figure 7.1 – Horizontal alignment by means of the machine feet
[1] Machine feet