SM-200 TE Grinding and Honing Machine 29
Putting the Machine into Operation
7
7.3 Removing the dressing tool
The SM-200 TE grinding and honing machine is delivered with the
dressing tool mounted. Remove the dressing tool next to the grind-
ing wheel before starting up the machine.
1 Loosen the clamping screw on the dressing tool.
2 Pull the dressing tool upwards out of the mounting.
3 Place the dressing tool in a suitable location.
7.4 Setting up the cooling water unit
The SM-200 TE grinding and honing machine with a stand is deliv-
ered with the cooling water unit fully installed.
The cooling water unit must be installed with the version without a
stand.
Position the cooling water unit at the SM-200 TE grinding and hon-
ing machine in such a way that the power supply, cooing water
hose and return hose can be easily attached.
The recommended position for the cooling water unit is below the
SM-200 TE grinding and honing machine.
Make the connections.
1 Place the water hose on the hose coupling below the cooling
water supply.
2 Place the return hose on the drain nozzle on the underside of
the belt safety tank. Guide the other end through the opening
in the lid into the water tank.
3 Place the power plug in the socket on the back of the
machine.
7.5 Filling the cooling water unit
Normal water suffices as cooling water.
1 Open the door on the stand.
2 Lift the cover with the pump out of the water tank.
3 Clean the water tank if necessary. To do this, remove the water
tank from the stand. Place the cleaned water tank in the stand.
4 Fill the water tank with cooling water to around 50 mm below
the rim.