d) Fill in the information as shown in the figure above. Tick the Use
Seasonal and set the time if you need to use Daylight Saving Time (DST).
Tick the “I agree that the power station can be remotely maintained and
functionally set by the agent/installer”, then your installer can assist you to
set the inverter remotely. Then touch Save to finish the registration.
3 Log in
Open the myEVERVOLT application and fill in your login account and password,
then touch Login to enter. It will be directly log in your account next time if you
tick the “Remember password”. Touch the “Forgot password” to refresh
password through your E-mail.
122
Appendix A: Wiring and Breaker Requirement
Inverter wiring
Inverter power terminal (Purchased separately)
1
2
3 8 AWG
No.
90°C(194°F), 600 V, copper
90°C(194°F), 600 V, copper
90°C(194°F), 600 V, copper
0.47 in / 12 mm
10-8 AWG
Cross-sectional Area Range
Strip Length
Terminals
PV terminals
AC terminals
Ground terminals
Type
0.47 in / 12 mm
0.47 in / 12 mm
10-8 AWG