7. Commissioning
7.1 Initial commissioning
• Documentthecommissioningprocedure(actionsandsettings).
• Checkthattheinstallationandotheractionspriortousehavebeencarriedoutinfull(e.g.powersupplyavailableand
connected,functioningoractivefuses,sealtightnessoftheequipment,transportprotectionofthevolumesensorremoved).
Caution:Ensurethatthebasicvesselisnotlleduntilallthecommissioningmeasureshavebeencompleted.
• Adjustthemanualcontrolvalveonthepumpmodule(seeappendix2).OntheM02,thesecondmanualcontrolvalvemustbe
set as well.
• Fillandde-aeratetheheatingorcoolingsystem(notthevessel!)
• Checktheoperationalreadinessofthetop-upline.
• Openthevalveatthetop-upconnectionandthelockshieldvalveattheexibleconnectionassembly(vesselconnection).
• Switchonthecontrolunitandrunthestartmenuprocedure(Ch7.3;overviewofmenu,entries;menulines9...9-99).
• Firstselecttherequiredlanguageinpoint4ofthemainmenu.
• DependingontheinitalcongurationinthestartmenuPoint9-5and9-6willappearinsteadof9-7.
• ThentheFlamcomatbasicvesselshallbeselectedbaseduponitsnominalcapacity(Ch5.2,name-plateVessel)and
consequentlythefactory-,operatingcalibrationshallbeperformed.
• Thisstart-upprocedureisfollowedbyactivatingthetop-upprocedure.Onceavolumelevelofapprox.7%hasbeenreached
(seedisplay),switchOFFthecontrolunitandde-aeratethepump(s)(Par.5.5;pos.3.5B;3.6B,page96;pos3.20).Onpumps
withautomaticde-aeration,thesemustbeopenedbyasingleturnoftheredcaponthesecomponents.
• Openthecapvalveonthereturncircuit(systemowandreturn)Caution,theheatingsystempipesmaybehot.
• Sealthelockshieldvalves.
• Thecompletionofallthetaskstobecarriedout,thereviewoftechnicaldata,recommendationsandexplanationsinthis
manual lead to the pressure expansion automat being ready for operation.
• SWITCH ON THE CONTROL UNIT.
Balancingvalvesonthepumpunitmaynotbeclosedduringoperationasdoingsomaycausesevere/destructivedamagetothe
pump unit.
ENG