Boost Pump Control
When the pump is first installed or high-pressure tubing
is replaced, you must purge the system by sending pres
-
surized water through it. Touch the [I] button while the
pump is off to energize the boost pump and purge the
system.
Note: The operator must block the bleed-down to
drain so the water can flow through the high-pressure
tubing, then open the bleed-down to drain when purging
is finished so the pump can operate normally.
Turn off the purge system by touching the [O] button,
by cycling power to the system, or by starting the pump.
Navigation
•
Touch the Main Run Screen button to return to the
Main Run Screen
•
Touch the Display Services button to continue to
the Display Services screen