GE HEALTHCARE
DIRECTION 5394141, REVISION 5 LOGIQ™ P5 SEVICE MANUAL
8-88 Section 8-2 - DISASSEMBLY/RE-ASSEMBLY
8-2-35 ASIG Assy
8-2-35-1 Tools
• Common pilIips screwdrivers
8-2-35-2 Preparations
• Shut down the system and switch off the main breaker.
8-2-35-3 Removal procedure
1.) Remove the Side Right Cover. Refer to the 8-2-16 "Side Right Cover" on page 8-52.
2.) Remove the EMI Cover R. Refer to the 8-2-27 "EMI Cover R" on page 8-69.
3.) Unscrew 2 screws (1-2) and eject the PCB.
4.) Perform the following functional tests. If all are successful, include the debrief script provided below.
8-2-35-4 Mounting Procedure
Install the new parts in the reverse order of removal.
Figure 8-122 Eject the ASIG
Table 8-36 Functional Tests
Service Manual
Section
Functional Test / Diagnostic Test Debrief Script
Section 4-3-1
Power On/Boot Up
“Service Manual, Direction
5394141, Rev 1+, Section 8-2-35. Equipment
passed all required tests and is ready for use. “
Section 4-3-2
Power Off / Shutdown
Section 4-9-16
ASIG ASSY Function Validation Procedure
Section 4-3-4
System B/M-Mode Checks
Section 4-3-5
System CFM and PWD Checks
Section 10-5-2
Functional Checks (See Also Chapter 4)