GE HEALTHCARE PROPRIETARY TO GE
D
IRECTION 5394227, 12 LOGIQ S8/LOGIQ E8 SERVICE MANUAL
4 - 48 Section 4-5 - Application Turnover Check List
Section 4-5
Application Turnover Check List
Complete these checks before returning the scanner to the customer for use:
4-5-1 Software Configuration Checks
Section 4-6
Power supply test and adjustments
4-6-1 Power Supply Test Procedure
Run the System Voltage test. Refer to 7-9-3 "System" on page 7-130.
4-6-2 Power Supply Adjustment
There are no adjustments on the power supplies. The DC Power is self-regulated. If a voltage is outside
the specified range, it means that something is wrong, either with the power supply itself or with a unit
connected to that specific power outlet.
Table 4-4 Software Configuration Checks
STEP TASK
CHECK ( )
1.
Check Date and Time setting
2.
Check that Location (Hospital Name & Department) is
correct
3.
Check Language settings
4.
Check assignment of Printer Keys
P1 P2 P3
5.
Check that all of the customer’s options are correctly
installed