EasyManua.ls Logo

GE Optima IGS 330 - Chapter 7 Appendix; 1 PIST0021 - US Fluoro UPS and PDB connection

GE Optima IGS 330
202 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Chapter 7 Appendix
1 PIST0021 - US Fluoro UPS and PDB connection
1.1 Personnel Requirements
Personnel
Requirements
Preliminary Reqs Procedure Finalization
1 Not Applicable 1 hour Not Applicable
1.2 Preliminary Requirements
1.2.1 Tools and Test Equipment
Item Qty Effectivity Part# Manufacturer
Standard Service
Engineer’s toolkit
1 - - -
1.2.2 Required Conditions
Condition Reference Effectivity
The PDB is already installed - -
Power cables are as follows: (1) From
PDB to UPS rectifier input = 4x6 AWG
recommended (4x3 AWG max) (3ph +
PE). (2) Bypass = 5x8 AWG
recommended (5x3 AWG max)(3ph + N
+PE). (3) From UPS output to PDB = 5x8
AWG recommended (5x3 AWG max)(3ph
+ N+PE)..
- -
Cable sizing shall follow local
requirements.
- -
Power cable Mechanical Terminals
Torque Specification: < 3 Nm / < 27 lb.in
for 20 AWG to 3 AWG.
- -
Check the UPS shipping date marked on
the packaging label. Commissioning of the
UPS must be performed within 3 months
after that date.
- -
Optima IGS 320, Optima IGS 330 Pre-Installation Manual
Direction 5537562-1-1EN, Revision 3
Chapter 7 Appendix 195

Table of Contents

Related product manuals