Chapter 2 Equipment Requirements
1 System Components
1.1 Presentation of the 3 Rooms
1.1.1 Examination room
Gantry
Omega Patient Table
Performix X–Ray Tube Assembly
Collimator
Digital Detector
TSUI
ITU
WARNING
THE ELECTRONIC CABINETS (SYSTEM CONTROL CABINET, OPTIONAL LD
CABINET, COOLIX 4100 CHILLER, DETECTOR CONDITIONER AND FLUORO
UPS WHEN INSTALLED) INCLUDE FANS THAT ARE CREATING AIR-
CIRCULATION OF PULSED-AIR. WHEN THIS PULSED AIR IS IN AN
ENVIRONMENT THAT MAY CONTAIN AIRBORNE PATHOGENS LIKE AN
EXAM ROOM/CONTROL ROOM, THERE IS A RISK OF TRANSMISSION OF
THESE AIRBORNE PATHOGENS FROM PATIENTS TO OTHER PATIENTS
OR CLINICAL PERSONNEL (NOSOCOMIAL DISEASES).
TO REDUCE THIS RISK, THE ELECTRONIC CABINETS MUST BE
INSTALLED IN A ROOM SEPARATED FROM EXAM ROOM/CONTROL ROOM,
I.E., TECHNICAL ROOM.
1.1.2 Technical room
System Control Cabinet
Coolix 4100 chiller
Detector Conditioner
Fluoro UPS (option) (1 Cabinet)
Fluoro UPS IF box (option)
PDB
EMC Filter (Option)
Optima IGS 320, Optima IGS 330 Pre-Installation Manual
Direction 5537562-1-1EN, Revision 3
Chapter 2 Equipment Requirements 43