3.5 European Process Order Select
Several components like cables, stationary rails, etc. are length selectable. This selection
should reflect the particularities encountered by an Installation Specialist on Site.
All cable and component selections must be sent at least 6 weeks before RSDD to your PMC.
The selection tool is available on the website: http://supportcentral.ge.com/products/
sup_products.asp?prod_id=99484
Optima IGS 320, Optima IGS 330 Pre-Installation Manual
Direction 5537562-1-1EN, Revision 3
38 3 Delivery Requirements