PROTEUS XR/a
GE MEDICAL SYSTEMS Operator Manual
REV 11 DIRECTION 2259724-100
11-4
OVER HEAD TUBE
SUSPENSION
Rail Stand Tracks 12 months Lubricate tracks with cloth slight moistened with
light oil.
Visual Checks and Operational
Tests
12 months Inspect and replace or repair as required:
• Loose hardware, loose wires, or shorted
electrical terminals
• Ground connections
• High tension cable connections at X-ray tube and
high voltage transformer
• Worn external cables and wires
• Bearing surfaces for cleanliness/corrosion
• Worn or damaged parts
• Steel aircraft cables Perform operational tests
Replacement 8 years
• Safety Reel and Cable (Complete safety reel
assembly). Reference to OTS Suspension
Service Manual chapter 4, Service Procedure.
COLLIMATOR
Maintenance Checklist 12 months Perform calibration procedures:
• X-ray field vs. indicated size
• X-ray field and receptor alignment
• Beam alignment
• Cross hairs to light field alignment
• Bucky light line alignment (auto only)
• Lubrication
Mounting Hardware 12 months Check tightness of collimator mounting bolts.
Lubrication 12 months Lubricate all moving parts
ACCESSORIES
Compression Band 12 months Check condition.
Patient hand grips 12 months Check condition.
Collimator Cone 12 months Check condition
WALL STAND (GPCP No.:
2260354)
Visual inspection 12 months Check for defects that would indicate abnormal
wear.
General cleaning and painting. As required. See section above.
Functional Checks 12 months Perform tasks described in Proteus XR/a service
manual.
SG120 WALL STAND (GPCP
No.: 2402562)
Visual inspection 18 months Check for defects that would indicate abnormal
wear.
General cleaning and painting. As required. See section above.
Functional Checks 18 months Perform tasks described in Proteus XR/a service
manual.
FOR TRAINING PURPOSES ONLY!
NOTE: Once downloaded, this document is UNCONTROLLED, and therefore may not be the latest revision. Always confirm revision status against a validated source (ie CDL).