PROTEUS XR/a
GE MEDICAL SYSTEMS Operator Manual
REV 11 DIRECTION 2259724-100
11-5
MECHANICAL
Counterweight chain 18 months Inspect and grease length of chains. Replace if
excessively rusty.
Carriage Roller Bearing
inspection.
18 months Clean roller bearings and tracks.
Vertical lock. 18 months Lock notched rail. General cleaning. Functional
check according to service manual.
11-5 Recycling
Packing Materials:
The materials used to pack our equipment are recyclable. They must be
collected and processed in accordance with the regulations in force for the
country where the machines or accessories are unpacked.
Machines or Accessories at end-of-life:
The elimination of machines and accessories must be in accordance with
national regulations for waste processing. All materials and components that
could pose a risk to the environment must be removed from the machines at
end-of -life and accessories (examples: dry and wet cell batteries, transformer
oil, etc.).
Please consult your local GEMS representative before discarding these
products.
FOR TRAINING PURPOSES ONLY!
NOTE: Once downloaded, this document is UNCONTROLLED, and therefore may not be the latest revision. Always confirm revision status against a validated source (ie CDL).

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the GE Proteus XR/a and is the answer not in the manual?