1. Push Maintenance>Replace Component.
2. Select an option.
Option Description
Replace Ozone Filter Shows the hourly usage of the ozone filter. Shows how to replace the ozone filter on
the display.
Replace UV Reactor Shows the hourly usage of the UV reactor. Shows how to replace the UV reactor on
the display.
Replace Syringe Shows how to replace the syringe on the display. Push Start to replace the syringe.
Clean Analyzer Flushes the instrument clean. The instrument controls the cleaning cycles. Push
Clean Analyzer to start the cleaning.
Install a firmware update
Locate the firmware update file on the product website. Save the file from the website to a USB flash
drive, then do the steps that follow to install the firmware upgrade.
1. Push Maintenance>Update Firmware.
2. Put the USB flash drive into a USB port. The firmware update starts.
3. Push Close Application when the update is complete.
Prepare for shipment
N O T I C E
The instrument must be decontaminated before it is shipped. All fluids must be drained from the instrument.
1. Push Maintenance>Prepare for Shipment.
2. Open the instrument door.
3. Remove the GLS water vessel. Refer to Product overview on page 5.
4. Discard the water into a drain.
5. Install the GLS water vessel back into the instrument.
6. Push Drain Analyzer to remove all liquid from the instrument.
7. When the instrument completes the draining procedure, the instrument is ready for shipment.
Troubleshooting
Problem Possible cause Solution
The measurement does not start. An error occurred during
measurement setup.
• Set the instrument power to off,
then to on.
• Contact technical support if
necessary.
The system test fails. An error occurred during the
system test.
• Make sure that the carrier gas
supply is correctly connected.
• Contact technical support if
necessary.
A hardware component failure
occurred.
The measurements take too much
time to complete and/or the results
are consistently too low.
The UV reactor is almost expired. Replace the UV reactor. Make sure
that there is a sufficient quantity of
carrier gas.
The fittings around the reactor are
loose.
Make sure that the fittings around
the reactor are tight.
18 English