Commissioning
Maximum time between commissioning and operation
Procedure
1. Make sure that the time between commissioning and operation is not more than 2
weeks. If this is not possible, speak to H.I.T.
Do a check on the gear unit
Procedure
1. Do a check on the gear oil level. Refer to
Measure the gear oil level
on page 40.
2. Make sure that all lubrication points for grease are filled.
3. Make sure that all safety covers are installed correctly.
Start instructions (backstop)
Caution: Do not turn the gear unit in the incorrect direction. This condition
causes damage to the backstop.
Procedure
1. Make sure that the backstop operates correctly.
Start instructions (heater)
Procedure
1. Do not start the gear unit if the temperature of the gear oil is not correct. For the
specification, refer to section
Additional gear oil specifications (heater)
on page 61.
Start instructions (force-feed lubrication, pump with a motor)
Procedure
1. Make sure that the pump goes on minimum 60 s before the gear unit starts.
2. For more instructions, refer to the service manual of the lubrication and cooling
system.
9
9.1
9.2
9.3
9.4
9.5
Commissioning
44
IM_405_002_EN

Table of Contents

Other manuals for Hansen P4

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Hansen P4 and is the answer not in the manual?

Hansen P4 Specifications

General IconGeneral
BrandHansen
ModelP4
CategoryIndustrial Equipment
LanguageEnglish

Related product manuals