APCQ CAPACITOR BANKS
© 2022 Hitachi Energy. All rights reserved
– Remove lateral panels in between cabinets
– Place the seal between the cubicles, place the cubicles side by side, assemble the 8 pins and interconnect them
mechanically with the 4 brackets as per Figure 34.
Figure 34: Interconnection of cubicles
6.6. Seismic design
HITACHI ENERGY can provide a type tested seismic design as per:
– IEC 60068-2-57: 2013
– IEEE 693:2005.