APCQ CAPACITOR BANKS
STATUS
Approved
SECURITY LEVEL
Public
DOCUMENT ID
9AKK107680A4136
RE V.
E
LANG.
en
PAGE
40/47
© 2022 Hitachi Energy. All rights reserved
.
APCQ
- Maintenance check list
Iss
ued by:
Date:
Regular maintenance procedure
OK/NOK
Check ambient temperature and equipment ventilation (should be within specification).
Isolate the APCQ capacitor bank from power supplies.
Open the front door panel.
Clear air inlet and outlet.
Clean all parts from dust and dirt.
Check fuses (shouldn’t be brown).
Switch on each power step manually with RVC/RVT Controller.
Check contactors and their good operation replace them if necessary.
Check operation of RVC/RVT Controller.
Measure capacitors currents (in the three phases) for every power step and record the
measurements1.
QCap
I Phase A
I Phase B
I Phase C
I Nominal
OK/NOK
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
Fan replacement
OK/NOK
Fans have to be replaced every 5 years (40 000 hours)
1
current measurements should be compared to previous measurements. If current is 10% lower than first
measurement, capacitors have to be replaced.
Nominal current is normally given by:
=
3
Where:
= current in one phase -
= Reactive power (kvar) on the power step -
3 = square root of three -
= RMS value of phase to phase voltage