72 ControlEdge HC900 Process & Safety Controller User and Installation Manual Revision 10
May 2019
Install (or verify correct installation of) enclosures for
ControlEdge HC900 Controllers and ancillary
equipment:
Mounting rails or flat-panels
(for cabinet with multiple ControlEdge HC900 Chassis):
grounding bus
barrier strip for AC power
Master control Relay
Mount Racks
Table 8 – Mount Rack
Install (or verify correct installation of) enclosures
(“closets”) for networking devices:
See Pre-installation planning
sections.
Note: Some networking
devices may share
enclosures with ControlEdge
HC900 Controller
components.
Install (or verify correct installation of):
External disconnect switches
Fuses
at the power source associated with input sensor or output
devices for I/O modules.
See I/O Module Installation
and Wiring on page 80.
Arrange and organize items to be installed at or near
enclosures.