78 ControlEdge HC900 Process & Safety Controller User and Installation Manual Revision 10
May 2019
Step
Procedure
Comments/References
3
Ensure that AC power to the
rack is disconnected.
Set controller module’s
communication ports to
desired settings (page 38).
Carefully place the Controller
Module in the rack,
immediately to the right of
the Power Supply. Fasten it
in place with two captured
screws at top and bottom.
Torque to 0,4-0,5 N.m
(3.5 4.4 Lb-In).
ATTENTION:
Do not install the battery at
this time. Installing the
battery(s) before the
controller is configured
can substantially shorten
battery life. Install under
power after the controller
configuration is complete.
(For more information, refer
to Battery
Installation/Replacement,
page 210.)
4
I/O will be installed later.
See Page 80.