8. Connect the cable to the system board.
9. If needed, install the optical drive.
10. Install the access panel .
11. Install the server in the rack.
12. Connect each power cord to the server.
13. Connect each power cord to the power source.
14. Power up the server.
ResultsResults
The installation is complete.
Installing an 8SFF optical driveInstalling an 8SFF optical drive
PrerequisitesPrerequisites
Install the 8SFF display port/USB/optical blank option.
Be sure you have the following:
The components included with the hardware option kit
T-10 Torx screwdriver
ProcedureProcedure
1. Power down the server .
2. Remove all power:
a. Disconnect each power cord from the power source.
b. Disconnect each power cord from the server.
3. Do one of the following:
a. Extend the server from the rack .
b. Remove the server from the rack .