2. If only one power supply is going to be installed in the redundant power supply cage, make sure that the
blank in the power supply bay 2 is firmly secured.
3. Install the power distribution board:
a. Align the notches on the board with the pins on the chassis.
b. Slide the board down to engage it fully with its connector.
c. Tighten the board thumbscrew.
4. Install the Smart Storage Battery holder:
a. Insert the holder tabs into their corresponding chassis slots, and then slide the holder down.
b. If the Smart Storage Battery cable was disconnected, connect it back.